3.A Overview of procedures
Generally, all Local Government Units (LGUs) include the application for electrical permits to the procedure for application of a Building Permit. The processing of building permits falls under the overall control and supervision of the Office of the Building Official (OBO) of the LGU.
In processing the electrical permits, the Electrical Division of the OBO shall see to it that the applicant complies with the standards and requirements on electrical safety in the Philippine Electrical Code (PEC), the Electrical Engineering Law, and the concerned LGU.
The applicant shall first submit certain administrative and technical requirements as specified by the LGU. The Electrical Division will then assess the completeness and correctness of the submitted documents and forms. If satisfied, the Electrical Division within the indicative period of time and after payment of the required fees by the applicant will then issue the Electrical permit.
When all of the electrical systems have been installed, the applicant submits a request for inspection to the Electrical Division. The Electrical Division then assesses and evaluates the installation at the site for compliance with the National Building Code and the Philippine Electrical Code, based on the plans and specifications of the building that were submitted to the agency. If satisfied, the Electrical Division then issues a Certificate of Final Electrical Inspection.
3.B Requirements
The following are the required documents to be submitted to the electrical division of the concerned LGU:
a. Electrical permit for new building (and installation of roof top solar PV)
Makati |
|
Manila |
|
Pasig |
|
Quezon City |
|
b. Electrical permit for new installation (e.g. rooftop solar PV) in an old or existing building
Makati |
|
Manila |
|
Pasig |
|
Quezon City |
|
C. Certificate of Final electrical inspection
Makati |
|
Manila |
|
Pasig |
|
Quezon City |
|
3.C Timeline
Upon submission of administrative requirements, each LGU has set a timeline for administrative action as follows:
Makati city | Manila | Pasig City | Quezon City | |
Approval of Electrical
Permit Upon submission
of documentary requirements
|
|
|
|
|
Shedule of Electrical inspection
upon submission of request for inspection
|
|
|
|
|
Issuance of Certificate of Final Electrical
Inspection after the final inspection
|
|
|
|
|
d.1 Total Connected load
d.1.1. | 5 kVA or less | P 200.00 | ||
d.1.2 | Over 5 kVA to 50kVA | 200.00 | + | 20.00/ kVA |
d.1.3. | Over 50 kVA to 300kVA | 1,100.00 | + | 10.00/ kVA |
d.1.4. | Over 300 kVA to 1,500kVA | 3,600.00 | + | 5.00/ kVA |
d.1.5. | Over 1,500.00 kVA to 6,000kVA | 9,600.00 | + | 2.50/ kVA |
d.1.6. | Over 6,000 kVA | 20,850.00 | + | 0.25/ kVA |
Note : Total connected load as shown in the load schedule.
d.2 Total transformer/uninterrupted power supply (UPS) /generator capacity (kVA)(or kW in the case of rooftop solar PV)
d.2.1. | 5 kVA or less | P 40.00 | ||
d.2.2 | Over 5 kVA to 50kVA | 40.00 | + | 4.00/ kVA |
d.2.3. | Over 50 kVA to 300kVA | 220.00 | + | 2.00/ kVA |
d.2.4. | Over 300 kVA to 1,500kVA | 720.00 | + | 1.00/ kVA |
d.2.5. | Over 1,500.00 kVA to 6,000kVA | 1,920.00 | + | 0.50/ kVA |
d.2.6. | Over 6,000 kVA | 4,170.00 | + | 0.25/ kVA |
Note : Total Transformer /UPS/ Generator Capacity shall include all transformer, UPS and generators which are owned/installed by the owner /applicant as shown in the electrical plans and specifications.
d.3 Pole/Attachment location plan permit
d.3.1. | Power Supply Pole Location | P | 30.00/pole |
d.3.2. | Guying attachment | 30.00/attachment |
This applies to design /installations within the premises
d.4 Miscellaneous fees: Electric meter for union seperation,alteration, reconnection, or relocation and issuance of wiring permit:
Use or Character of Occupancy | Electric Meter | Writing Permit Issuance |
Residential | P 15.00 | P 15.00 |
Commercial/industrial | 60.00 | 36.00 |
Institutional | 30.00 | 12.00 |
d.5 Formula for computation of fees
The Total Electrical Fees shall be the sum of d.1 to d.4
d.6 Forfeiture of fees
If the Electrical work or Installation is found not in conformity with the minimum safety requirements of tghe philippine Electrical Codes and the Electrical Engineering Law (RA 7920), and the Owner fails to perform corrective actions within the reasonable time provided by the building official, the latter and/or their duly authorized representatives shall forthwith cancel the permit and the fees thereonb shall be forfeited.