Power Situation Update 2 May 2019 (as of 1:00 PM)

GRID STATUS:           NORMAL CONDITION

LUZON POWER PLANT OUTAGES/DERATED

As of 1:00 PM, 2 May 2019, Thursday

Forced Outage (due to Earthquake)

Power Plant

Installed Capacity (MW)

Dependable Capacity (MW)

Cause

Date Out

Estimated Date In

GNPower Mariveles Power  Ltd. (GMPC) U2

345

316

Isolated due tripping of Transmission line caused by 6.1 magnitude earthquake

22-Apr-2019

2-May-2019

Total

345

316

 

 

 

 

 

 

Unplanned/Forced Outage

Power Plant

Installed Capacity (MW)

Dependable Capacity (MW)

Cause

Date Out

Estimated Date In

SEM-Calaca Power Corporation (SCPC)

Calaca U2

300

200

Boiler Tube Leak

28-Apr-2019

4-May-2019

Angat Main Unit 3

50

50

Tripped due to High Bearing Temperature

29-Apr-2019

TBD

Total

300

250

 

 

 

 

 

 

De-rated/Reduced Capacity

Power Plant

Installed Capacity (MW)

Declared Capacity (MW)

Derating/ Reduced Capacity (MW)

Cause

Pagbilao Energy Corporation (PEC) Pagbilao U3

420

270

150

Boiler condition under assessment

Total

 

 

150

 

 

Source: NGCP, concerned power plants

TBD – To be determined