The provisions of Department Circular No. DC2020-11-024 or the OCSP3 Guidelines are hereby amended as follows:

Additional information:

Annex B. Checklist of Requirements. –

  • We require that the applicant submit the corporate documents of all Filipino stockholders, (1) to provide standard requirements, without the need to restate case law, and the tests utilized to determine compliance with the rules on foreign participation in nationalized industries, and (2) to avoid any and all issues that may arise during the opening of bids and the subsequent evaluation.
  • Regarding the requirement of consularization / apostilization of the curriculum vitae of foreign consultants and contracts signed outside the Philippines (technical qualifications): In view of the closure or suspension of services of foreign embassies/consular offices abroad due to the COVID-19 pandemic, the applicant may submit:

a. A sworn affidavit executed by the authorized representative attesting to such fact;

b. Proof of closure or suspension of service of such foreign embassy/consular office; and

c. Curriculum vitae and contracts.

We have taken note of the Consolidated Comments and Inquiries posted as of August 27, 2020. We wish to state, however, that these shall in no way affect or change the contents of the OCSP3 Guidelines and its subsequent supplemental bid bulletins.

 

Clarification on the Pre-determined Areas for Hydropower Resources

1. The capacity of Area 17 -Balintingon Hydroelectric Power Project is 52 MW based on the updated feasibility study submitted to the DOE.