CHECKLIST OF REQUIREMENTS
QUALIFIED THIRD PARTY CERTIFICATE OF ENDORSEMENT TO THE ENERGY REGULATORY COMMISSION (QTP-COE TO ERC)
- Letter of Request addressed to the EPIMB Director
- Company Profile
- Project Background/ Description to include at least the following:
- Name of the generating facility
- Nameplate Capacity (including photographs of nameplate attached to the machine)
- Exact Location
- Target Commercial Operation; and
- Jobs Generated (During Construction and During Operation)
- Copy of Resolution of Award of the QTP BAC duly signed by the QTP BAC Chairperson
- SEC Registration
- Articles of Incorporation
- By-Laws of the Company
- Copy of QTP Service Contract
Additional for ERC COC Renewal:
- Copy of the ERC Certificate of Compliance (COC)
- Certification of new rated capacity (if applicable)
Additional for Renewable Energy Power Projects:
- Copy of the DOE RE Service Contract or RE Certificate of Registration (Whichever is applicabe)