DU Bid Bulletin
Distribution Utility | Demand (MW) Energy (MWh) | Contract Period | DU CSP Stage | Date Posted | PDF file | |
---|---|---|---|---|---|---|
BATELEC II |
Pre-Bid ConferencePre-bid Conference for the 5 MW Firm Baseload CSP May 25, 2021 |
5 MW | Eight (8) years from June 26, 2022 to June 25, 2030 | Pre-Bid Conference | January 25, 2021 | BATELEC II_5 MW TOR for Baseload Requirements_compressed.pdf |
BATELEC II |
Issuance of Bid DocumentsIssuance of Bid Documents for the 5 MW Firm Baseload CSP May 24, 2021 |
5 MW | Eight (8) years from June 26, 2022 to June 25, 2030 | Issuance of Bid Documents | January 25, 2021 | BATELEC II_5 MW TOR for Baseload Requirements_compressed.pdf |
BATELEC II |
Pre-Bid ConferencePre-Bid Conference for the 5MW CSP for RPS March 8, 2021 |
5 MW | Nine (9) years from December 26, 2021 to 25 December 2030 | Pre-Bid Conference | January 25, 2021 | BATELEC II_5 MW TOR for RPS Compliance_compressed.pdf |
BATELEC II |
Issuance of Bid DocumentsIssuance of Bid Documents for the 5 MW CSP for RPS March 4, 2021 |
5 MW | Nine (9) years from December 26, 2021 to 25 December 2030 | Issuance of Bid Documents | January 25, 2021 | BATELEC II_5 MW TOR for RPS Compliance_compressed.pdf |
BATELEC II |
Invitation to BidPublication of Invitation to Bdders for the procurement of 5 MW Firm Baseload power requirements 1. 1st Publication of Invitation to Bidders: May 7, 2021 2. 2nd Publication of Invitation to Bidders: May 14, 2021 |
5 MW | Eight (8) years from June 26, 2022 to June 25, 2030 | Invitation to Bid | January 25, 2021 | BATELEC II_5 MW TOR for Baseload Requirements_compressed.pdf |
BATELEC II |
Invitation to BidPublication of Invitation to Bidders for the procurement of 5 MW power requirement for RPS 1. Ist Publication of Invitation to Bidders: February 16, 2021 2. 2nd Publication of Invitation to Bidders: February 23, 2021 |
5 MW | Nine (9) years from December 26, 2021 to 25 December 2030 | Invitation to Bid | January 25, 2021 | BATELEC II_5 MW TOR for RPS Compliance_compressed.pdf |
SEZ |
Issuance of Bid BulletinSEZ_Supplemental Bid Bulletin No. 3: Matters arising from the Pre-Bid Conference |
10 MW (5 MW short-term and 5 MW long-term) | 5 years | Issuance of Bid Bulletin | January 22, 2021 | SEZ_Supplemental Bid Bulletin No. 3.pdf |
LEZ |
Invitation to BidPre-qualification meeting: Availability of Bid Documents: Deadline of submission of comments and questions on the Bid: Pre-Bid Conference meeting: |
9 MW (minimum bid of 3 MW) | 5 years | Invitation to Bid | January 21, 2021 | LEZ_Invitation to Submit Proposal (2nd round).pdf |
MERALCO |
Submission and Opening of BidsSubmission and Opening of Bids January 27, 2021 @ 8:00 AM Virtual via Zoom |
1800 MW | 20 years | Submission and Opening of Bids | January 20, 2021 | |
LUECO |
Supplemental Bid BulletinSupplemental Bid Bulletins 1 to 3: 1. Additional Contact Numbers; 2. Revised Confidentiality Undertaking; and 3. Amended Pre-Bid Conference Schedule: - February 4, 2021 at 9:00 AM via Zoom |
43 MW to 64 MW | Commencement date up to 25 February 2032 | Supplemental Bid Bulletin | January 11, 2021 |
Bid Bull No. 1 additional contact numbers.pdf Bid Bull No. 2 Revised Confidentiality Undertaking.pdf Bid Bull No. 3 Amended PRE-BID Conference Schedule.pdf |