DU Bid Bulletin

Distribution Utility Demand (MW) Energy (MWh) Contract Period DU CSP Stage Date Posted PDF file
DLPC
Supplemental Bid Bulletin No. 2

DLPC 2nd round of CSP for the procurement of 55 MW Intermediate Power Requirements (75% from eligible RE) for RPS compliance

Supplemental Bid Bulletin No. 2

Revised DLPC TOR adopting the comments/suggestions during the Pre-Bid Conference

 

55 MW Intermediate and RE power supply requirements for RPS compliance Ten (10) years staring February 26, 2022, subject to the approval of the Energy Regulatory Commission Supplemental Bid Bulletin No. 2 November 2, 2021 PDF icon DLPC SBB No. 2-Revised 55 MW TOR-result of 2nd round of CSP-Pre-Bid Conference.pdf
DLPC
Issuance of Notice of Award

DLPC 2nd round of CSP for the procurement of 55 MW Intermediate (75% from eligible RE) power supply requirements for RPS compliance

Issuance of Notice of Award

24 November 2021

 

55 MW Intermediate and RE power supply requirements for RPS compliance Ten (10) years staring February 26, 2022, subject to the approval of the Energy Regulatory Commission Issuance of Notice of Award October 26, 2021 PDF icon DLPC_ITSP and CSP Schedule of Activities_2nd round CSP.pdf
DLPC
Post Qualification

DLPC 2nd round of CSP for the procurement of 55 MW Intermediate (75% from eligible RE) power supply requirements for RPS compliance

Post Qualification

24 November 2021

1:30 PM

55 MW Intermediate and RE power supply requirements for RPS compliance Ten (10) years staring February 26, 2022, subject to the approval of the Energy Regulatory Commission Post Qualification October 26, 2021 PDF icon DLPC_ITSP and CSP Schedule of Activities_2nd round CSP.pdf
DLPC
Opening and Evaluation of Bids

DLPC 2nd round of CSP for the procurement of 55 MW Intermediate (75% from eligible RE) power supply requirements

Opening and Evaluation of Bids (Provisional Declaration of Winning Bidder)

17 November 2021

9:00 AM

55 MW Intermediate and RE power supply requirements for RPS compliance Ten (10) years staring February 26, 2022, subject to the approval of the Energy Regulatory Commission Opening and Evaluation of Bids October 26, 2021 PDF icon DLPC_ITSP and CSP Schedule of Activities_2nd round CSP.pdf
DLPC
Deadline of Submission of Bids (Bid Submission)

DLPC 2nd round of CSP for the procurement of 55 MW Intermediate (75% from eligible RE supply) for RPS compliance

Deadline of Submission of Bids (Bid Submission)

17 November 2021

9:00 AM

55 MW Intermediate and RE power supply requirements for RPS compliance Ten (10) years staring February 26, 2022, subject to the approval of the Energy Regulatory Commission Deadline of Submission of Bids (Bid Submission) October 26, 2021 PDF icon DLPC_ITSP and CSP Schedule of Activities_2nd round CSP.pdf
AEC
Supplemental Bid Bulletin

Supplemental Bid Bulletin No. 1

13 MW 10 years Supplemental Bid Bulletin October 25, 2021 PDF icon 00 Bid Bulletin No. 01-25.Oct_.2021.AEC-CSP-RPS-2021-01.pdf
PDF icon 01 AEC-RPS-CSP-TOR (As Amended on 25.Oct_.2021).pdf
PDF icon 02 Annex 01-AEC-RPS-CSP-ITB (as amended on 25.Oct_.2021).pdf
PDF icon 03 Annex 02-AEC-RPS-CSP-PSA Template (As Amended on 25.Oct_.2021).pdf
PDF icon 04 Annex 03 AEC-RPS-CSP-BCQ Nomination (As Amended on 25.Oct_.2021).pdf
PDF icon 07 AEC-TPBAC Response to AC Energy Queries.25.Oct_.2021.pdf
PDF icon 08 AEC-TPBAC to BGI Queries.25.Oct_.2021.pdf
PDF icon 09 AEC-TPBAC Response to SNAP-BI queries.25.Octo_.2021.pdf
MERALCO
Supplemental Bid Bulletin

Supplemental Bid Bulletin Nos. 1 and 2

70 MW 20 years Supplemental Bid Bulletin October 25, 2021 PDF icon 70MWCSP BB1and2 Submission to DOE-2-6.pdf
DLPC
Supplement Bid Bulletin No. 1

DLPC 2nd round of CSP for the CSP of 55 MW Intermediate RE for RPS compliance

SBB No. 1 Postponement of Pre-Bid Conference on 25 October 2021 and moved to 26 October 2021, 9:00 AM to 5:00 PM

55 MW Intermediate and RE power supply requirements for RPS compliance Ten (10) years staring February 26, 2022, subject to the approval of the Energy Regulatory Commission Supplemental Bid Bulletin No. 1 October 22, 2021 PDF icon SBB 1 [2nd Round]_Postponement of Pre-Bid Conference on 25 October 2021 and moved to 26 October 2021.pdf
QUIRELCO
Supplemental Bid Bulletin

Supplemental Bid Bulletin Nos. 9, 10, & 11

15 MW 5 years Supplemental Bid Bulletin October 11, 2021 PDF icon SBB-No.2021-09.pdf
PDF icon SBB No.2021-10.pdf
PDF icon SBB No.2021-11.pdf
AEC
Invitation to Bid

Corrected (As of 15 October 2021)

Issuance of Bid Documents
October 18, 2021

1st Pre-Bid Conference
October 21, 2021, 10:00 AM

2nd Pre-Bid Conference (if needed)
October 28, 2021, 10:00 AM

13 MW 10 years Invitation to Bid October 11, 2021 PDF icon 01 AEC-RPS-CSP-TOR.pdf
PDF icon 02 Annex 01-AEC-RPS-CSP-ITB.pdf