FOR PRE-DETERMINED AREAS
DATE | ACTIVITY |
Day 1 | Launching of PCECP |
Day 1 + 180 calendar days, on or before 1100H to be submitted at the DOE Records Section |
Deadline for the submission of documents by PDA applicants |
Day 1 + 180 calendar days, 1330H, at the DOE-AVR or as determined by the REC |
Opening of documents |
Day 181 + 15 working days | Evaluation of documents |
Day 196 + 5 working days | Endorsement of Award of Petroleum Service Contract |
FOR NOMINATED AREAS
DATE | ACTIVITY |
Day 1 | Publication date of Nominated Area |
Day 1 plus sixty (60) calendar days (2 months) on or before 1100H at the DOE Records Section |
Deadline for the Submission of documents by Applicants |
Day 1 plus sixty (60) calendar days (same day as Deadline of Submission of Documents) 1300H at the DOE AVR |
Opening of documents |
Day 61 + 15 working days | Evaluation of documents |
Day 76 + 5 working days | Endorsement of Award of Petroleum Service Contract |