SOCOTECO II
DU Demand:
At least 85,000 MWh Dispatchable Energy
DU Contract Period:
End of Year 2022 assuming ERC approval of the PSA for 15 years from start of commercial operation
DU CSP Stage:
Pre-Bid Conference
SOCOTECO II CSP for the procurement of At Least 85,000 MWh Dispatchable Energy
1. 1st Pre-Bid Conference
December 15, 2021, 9:00 AM
Note: Pre-condition of A.P.O.R. to quarantine policy of L.G.U.
2. Issuance of Bid Bulletin/s, if any
January 4, 2022
3. Deadline for Eligibility Requirements and Submission of Bids ("Bid Submission Deadline")
January 18, 2022, 9:00 AM via SOCOTECO II Portal