PRESS RELEASE
05 October 2026
DOE: NGCP Reserves Failure Exposed Visayas to Red and Yellow Alerts
The Department of Energy (DOE) said the recent yellow and red alerts in the Visayas could have been avoided had the National Grid Corporation of the Philippines (NGCP)completed critical ancillary service contracts on time.
As early as May 22, 2026, the DOE directed NGCP to execute Ancillary Services Procurement Agreements (ASPAs) for at least 250 megawatts (MW) of Visayas reserves. The DOE had identified the need for additional reserves to strengthen the power system’s reliability and security, following the declaration of a State of National Energy Emergency under Executive Order No. 110.
Further directives, primarily addressing the critical power situation in the Visayas, were issued to NGCP on May 27, June 16, June 18, and August 3. NGCP’s failure to fully execute and file the required agreements led the DOE to issue a Show Cause Order on August 13.
“We saw the risk as early as May and directed NGCP to secure the necessary reserves. The batteries were there. The Visayas needed these reserves on the grid months ago. What was missing was timely execution. Delays in contracting left consumers with less protection when generating units unexpectedly went offline,” Energy Secretary Sharon S. Garin said.
Battery energy storage systems (BESS) can provide fast-response reserves when generating units experience unforeseen outages, helping the System Operator stabilize the grid and prevent supply shortages from escalating into yellow or red alerts.
The contracting delays have implications not only for grid reliability but also for electricity costs. Firm ancillary service contracts provide committed reserves that can lessen dependence on the Reserve Market, where prices can rise sharply during periods of tight supply. A simulation conducted by the Independent Electricity Market Operator of the Philippines (IEMOP) found that the timely delivery of the reserves could have prevented the yellow and red alerts, and helped mitigate high electricity market prices. The simulation projected that delays in completing and executing these ASPAs could result in at least 10 red alerts and 30 yellow alerts, with electricity market prices averaging above 12 pesos per kilowatt-hour. Timely contracting could therefore have provided the Visayas grid with a stronger reserve buffer while reducing consumers’ exposure to volatile reserve-market prices.
The recurring grid alerts and rotational power interruptions have also placed additional pressure on businesses in the Visayas. DOE’s findings indicate that the recent power interruptions disrupted production and commercial operations, reduced operating hours, and promptedbusinesses to rely on generator sets and other backup power sources, adding to operating costs. Through the DOE’s coordination with business and industryassociations, the Department also found that thesedisruptions have been particularly difficult for micro, small, and medium enterprises, which have less capacity to absorb prolonged interruptions and additional energy expenses.
Despite the DOE’s repeated directives and coordination with NGCP to secure an affordable and reliable power system, the required connections, testing, commissioning, and completion of the ASPAs remained pending. These are critical steps requiring action from NGCP in its role as System Operator and transmission service provider.
The DOE has also raised concerns over transmission constraints that limit the transfer of available capacity across the Visayas. In particular, congestion and security limits on key interconnections have restricted the flow of additional electricity from Luzon to Leyte and from Leyte to Cebu, reducing the grid’s ability to move available power where it is needed.
The Department has repeatedly called NGCP’s attention to these constraints and directed it to accelerate critical transmission projects needed to relieve congestion and strengthen transfer capacity in the Visayas. The DOE has likewise directed NGCP to ensure that the necessary transmission infrastructure is ready to connect critical power generation facilities to the grid, consistent with the results of their respective System Impact Studies (SIS). The Department has also emphasized the need for the timely implementation of the Transmission Development Plan and the prioritization of infrastructure required to address persistent transmission constraints.
“As System Operator, NGCP must maintain sufficient reserves to protect the grid. It must also ensure that adequate transmission infrastructure is completed on time so electricity can flow where it is needed. Every part of the power system has a responsibility, and the DOE will work with Congress to hold each accountable,” Secretary Garin said.
The DOE is committed to ensuring the delivery of reliable and affordable power, for the benefit of every Filipino household. The DOE, in coordination with Congress and government stakeholders, will pursue accountability for failures that have contributed to the recurring power alerts in the Visayas.
The DOE continues to exercise its regulatory and oversight authority to ensure that directives intended to protect the reliability and security of the country’s power system are acted upon fully and on time. Continued non-compliance may result in administrative proceedings, penalties, sanctions, and other legal remedies.